Construction updates

October 22 - October 29

Riverside Ave. at Bernard St. & Division St. | Columbus St. & Mission Ave. | Napa St. & Mission Ave. Westbound | Wall St. | Mission Ave. & Perry St. Westbound

Completed Stations Phase I

Railings are being installed at the stations that have been completed in Phase I of construction.

Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17

Work includes foundations for City Line amenities, ADA improvements, and  landscape improvements. 

  • Avista vault work

Construction at this location is planned to be completed in November. View the Phase I traffic control plan here. View the Phase II traffic control plan here. 

Columbus Street and Mission Avenue Westbound – City Line Station 22

Work includes foundations for City Line amenities, ADA improvements, and  landscape improvements. 

  • Curbing
  • Bus platform

Construction at this location is planned to be completed in October. View the Left Lane traffic control plan here. View the Right Lane traffic control plan here. 

Perry Street and Mission Avenue Westbound – City Line Station 24

Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements. 

  • Platform installation
  • Paving

Construction at this location is planned to be completed in October. View the traffic control plan here.

Napa Street and Mission Avenue Westbound – City Line Station 25a

Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements. 

  • Paving
  • Platform installation
  • Landscaping

Construction at this location is planned to be completed in October. View the traffic control plan here.

Wall Street Roadwork – between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Tile installation
  • Curbing

Construction at this location is planned to be completed in November. View the traffic control plan here.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

October 15 - October 22

Riverside Ave. at Bernard St. & Division St. | Columbus St. & Mission Ave. | Napa St. & Mission Ave. Westbound | Wall St. | Mission Ave. & Perry St. Westbound

Completed Stations Phase I

Railings are being installed at the stations that have been completed in Phase I of construction.

Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17

Work includes foundations for City Line amenities, ADA improvements, and  landscape improvements. 

  • Demolition
  • Avista vault work

Construction at this location is planned to be completed in November. View the Phase I traffic control plan here. View the Phase II traffic control plan here. 

Columbus Street and Mission Avenue Westbound – City Line Station 22

Work includes foundations for City Line amenities, ADA improvements, and  landscape improvements. 

  • Electrical conduit
  • Concrete bus pads
  • Curbing

Construction at this location is planned to be completed in October. View the Left Lane traffic control plan here. View the Right Lane traffic control plan here. 

Perry Street and Mission Avenue Westbound – City Line Station 24

Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements. 

  • Platform installation
  • Sidewalks

Construction at this location is planned to be completed in October. View the traffic control plan here.

Napa Street and Mission Avenue Westbound – City Line Station 25a

Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements. 

  • Concrete work
  • Sign revision

Construction at this location is planned to be completed in October. View the traffic control plan here.

Wall Street Roadwork – between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Tile installation
  • Curbing

Construction at this location is planned to be completed in November. View the traffic control plan here.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

October 8 - October 15

Columbus St. & Mission Ave. | Napa St. & Mission Ave. Westbound | Wall St. | Mission Ave. & Perry St. Westbound

Completed Stations Phase I

Railings are being installed at the stations that have been completed in Phase I of construction.

Columbus Street and Mission Avenue Westbound – City Line Station 22

Work includes foundations for City Line amenities, ADA improvements, and  landscape improvements. 

  • Demolition work
  • Concrete bus pad

Construction at this location is planned to be completed in October. View the Left Lane traffic control plan here. View the Right Lane traffic control plan here. 

Perry Street and Mission Avenue Westbound – City Line Station 24

Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements. 

  • Platform installation
  • Sidewalks

Construction at this location is planned to be completed in October. View the traffic control plan here.

Napa Street and Mission Avenue Westbound – City Line Station 25a

Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements. 

  • Driveway approach
  • Concrete walkways
  • Platform installation

Construction at this location is planned to be completed in October. View the traffic control plan here.

Wall Street Roadwork – between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Tile installation

Construction at this location is planned to be completed in November. View the traffic control plan here.

October 1 - October 8

Cook St. & Mission Ave. Eastbound & Westbound | Napa St. & Mission Ave. Westbound | Wall St. | Mission Ave. & Perry St. Westbound

Completed Stations Phase I

Railings are being installed at the stations that have been completed in Phase I of construction.

Perry Street and Mission Avenue Westbound – City Line Station 24

Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements. 

  • Curb installation
  • Footing construction
  • Platform construction
  • Sidewalk installation
  • Electrical installation
  • Asphalt paving

Construction at this location is planned to be completed in October. View the traffic control plan here.

Napa Street and Mission Avenue Westbound – City Line Station 25a

Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements. 

  • Driveway approach
  • Concrete walkways
  • Footing construction
  • Electrical installation
  • Asphalt paving

Construction at this location is planned to be completed in October. View the traffic control plan here.

Cook Street and Mission Avenue Westbound – City Line Station 26a

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Platform construction

Construction at this location is planned to be completed in October. View the traffic control plan here.

Wall Street Roadwork – between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Tile installation

Construction at this location is planned to be completed in November. View the traffic control plan here.

September 23 - October 1

Cook St. & Mission Ave. Eastbound & Westbound | Napa St. & Mission Ave. Westbound | Wall St. | Mission Ave. & Perry St. Westbound

Completed Stations Phase I

Railings are being installed at the stations that have been completed in Phase I of construction.

Perry Street and Mission Avenue Westbound – City Line Station 24

Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements. 

  • Demolition work

Construction at this location is planned to be completed in October. View the traffic control plan here.

Napa Street and Mission Avenue Westbound – City Line Station 25a

Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements. 

  • Demolition work

Construction at this location is planned to be completed in October. View the traffic control plan here.

Cook Street and Mission Avenue Westbound – City Line Station 26a

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • City vault adjustment
  • Asphalt paving
  • platform construction

Construction at this location is planned to be completed in October. View the traffic control plan here.

Wall Street Roadwork – between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Light pole installation
  • Irrigation installation

Construction at this location is planned to be completed in November. View the traffic control plan here.

September 16 - September 23

Cook St. & Mission Ave. Eastbound | Napa St. & Mission Ave. Eastbound & Westbound | Wall St.

Completed Stations Phase I

Railings are being installed at the stations that have been completed in Phase I of construction.

Napa Street and Mission Avenue Westbound – City Line Station 25a

Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements. 

  • Demolition work

Construction at this location is planned to be completed in September. View the traffic control plan here.

Napa Street and Mission Avenue Eastbound – City Line Station 25b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Platform construction
  • Sidewalks

Construction at this location is planned to be completed in September. View the traffic control plan here.

Cook Street and Mission Avenue Westbound – City Line Station 26a

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Bus pad construction
  • Electrical installation
  • Curb installation
  • Platform construction

Construction at this location is planned to be completed in October. View the traffic control plan here.

Wall Street Roadwork – between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Light pole installation

Construction at this location is planned to be completed in November. View the traffic control plan here.

September 9 - September 16

Cook St. & Mission Ave. Eastbound | Napa St. & Mission Ave. Eastbound | Wall St.

Completed Stations Phase I

Railings are being installed at the stations that have been completed in Phase I of construction.

Cook Street and Mission Avenue Westbound – City Line Station 26a

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Demolition Work

Construction at this location is planned to be completed in October. View the traffic control plan here.

Napa Street and Mission Avenue Eastbound – City Line Station 25b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Sidewalk repoured
  • Footings install
  • Electrical conduit install

Construction at this location is planned to be completed in September. View the traffic control plan here.

Wall Street Roadwork – between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Light pole base installation
  • Irrigation installation

Construction at this location is planned to be completed in November. View the traffic control plan here.

September 3 - September 9

Spokane Falls Blvd. & WSU Spokane | Cook St. & Mission Ave. Eastbound | Napa St. & Mission Ave. Eastbound | Wall St.

Completed Stations Phase I

Railings are being installed at the stations that have been completed in Phase I of construction.

Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Curb installation 
  • Landscaping work
  • Striping and signing 
  • Construction clean up

Construction at this location is planned to be completed in August. View the traffic control plan here.

Cook Street & Mission Avenue Eastbound – City Line Station 26b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Electrical & communications installation
  • Backfill around footings 
  • Platform concrete pour
  • Street paving

Construction at this location is planned to be completed in September. View the traffic control plan here.

Napa Street and Mission Avenue Eastbound – City Line Station 25b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Gas line intallation
  • Electrical installation
  • Bus pad concrete pour

Construction at this location is planned to be completed in September. View the traffic control plan here.

Wall Street Roadwork – between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Light pole base installation
  • Work on tree wells

Construction at this location is planned to be completed in November. View the traffic control plan here.

August 27 - September 3

Spokane Falls Blvd. & WSU Spokane | Cook St. & Mission Ave. Eastbound | Napa St. & Mission Ave. Eastbound | Wall St.

Completed Stations Phase I

Railings are being installed at the stations that have been completed in Phase I of construction.

Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Curb installation 
  • Landscaping work
  • Construction clean up

Construction at this location is planned to be completed in August. View the traffic control plan here.

Cook Street & Mission Avenue Eastbound – City Line Station 26b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Electrical & communications installation
  • Backfill around footings 
  • Platform concrete pour

Construction at this location is planned to be completed in September. View the traffic control plan here.

Napa Street and Mission Avenue Eastbound – City Line Station 25b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Electrical installation
  • Bus pad concrete pour

Construction at this location is planned to be completed in September. View the traffic control plan here.

Wall Street Roadwork – between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Light pole base installation
  • Work on tree wells

Construction at this location is planned to be completed in November. View the traffic control plan here.

August 20 -August 27

Spokane Falls Blvd. & WSU Spokane | Cincinnati St. & Springfield Ave. | Cook St. & Mission Ave. Eastbound | Napa St. & Mission Ave. Eastbound | Wall St.

Completed Stations Phase I

Railings are being installed at the stations that have been completed in Phase I of construction.

Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Heated platform pipe installation
  • Platform concrete
  • Curbing and landscaping

Construction at this location is planned to be completed in August. View the traffic control plan here.

Cincinnati Street & Springfield Avenue – City Line Station 20

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Sign installation
  • Striping
  • Cleanup

Construction at this location is planned to be completed in August. View the traffic control plan here.

Cook Street & Mission Avenue Eastbound – City Line Station 26b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Bus pad construction
  • Curbing
  • Electrical installation

Construction at this location is planned to be completed in September. View the traffic control plan here.

Napa Street and Mission Avenue Eastbound – City Line Station 25b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Demolition work

Construction at this location is planned to be completed in September. View the traffic control plan here.

Wall Street Roadwork – between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Electrical conduit installation
  • Tile removal continues

Construction at this location is planned to be completed in November. View the traffic control plan here.

August 13 -August 20

Spokane Falls Blvd. & WSU Spokane | Cincinnati St. & Springfield Ave. | Cook St. & Mission Ave. Eastbound | Wall St.

Completed Stations Phase I

Railings are being installed at the stations that have been completed in Phase I of construction.

Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Landscaping
  • Sidewalk construction
  • Footing construction 

Construction at this location is planned to be completed in August. View the traffic control plan here.

Cincinnati Street & Springfield Avenue – City Line Station 20

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Landscaping
  • Platform concrete

Construction at this location is planned to be completed in August. View the traffic control plan here.

Cook Street & Mission Avenue Eastbound – City Line Station 26b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Tree trimming
  • Demolition

Construction at this location is planned to be completed in September. View the traffic control plan here.

Wall Street Roadwork – between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Electrical conduit installation
  • Tile removal continues

Construction at this location is planned to be completed in November. View the traffic control plan here.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 
 

Upcoming Projects:

  • Station 25b at Mission Avenue and Napa Street eastbound is scheduled to begin construction Aug 25. 
  • Station 26a at Mission Avenue and Cook Street wesbound is scheduled to begin construction Sept 6. 
Businesses remain open, please join STA in supporting local businesses throughout the construction season. 
 

Upcoming Projects:

  • Station 25b at Mission Avenue and Napa Street eastbound is scheduled to begin construction Aug 25. 
  • Station 26a at Mission Avenue and Cook Street wesbound is scheduled to begin construction Sept 6. 

August 6 -August 13

Spokane Falls Blvd. & WSU Spokane | Cincinnati St. & Springfield Ave. | Wall St.

Completed Stations Phase I

Railings are being installed at the stations that have been completed in Phase I of construction.

Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Landscaping
  • Seat wall construction
  • Sidewalk construction
  • Footing construction

Construction at this location is planned to be completed in July. View the traffic control plan here.

Cincinnati Street & Springfield Avenue – City Line Station 20

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Landscaping
  • Asphalt paving
  • Entrance concrete construction

Construction at this location is planned to be completed in August. View the traffic control plan here.

Wall Street Roadwork – between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Electrical conduit installation
  • Tile removal

Construction at this location is planned to be completed in November. View the traffic control plan here.

July 29 - August 6

Spokane Falls Blvd. & WSU Spokane | Cincinnati St. & Springfield Ave. | Wall St.

Completed Stations Phase I

Station railings are being installed at the stations that have been completed in Phase I of construction.

Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Landscaping
  • Seat wall construction

Construction at this location is planned to be completed in July. View the traffic control plan here.

Cincinnati Street & Springfield Avenue – City Line Station 20

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Sidewalks
  • Landscaping
  • Asphalt paving 

Construction at this location is planned to be completed in August. View the traffic control plan here.

Wall Street Roadwork – between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Electrical conduit installation

Construction at this location is planned to be completed in November. View the traffic control plan here.

July 22 - July 29

Spokane Falls Blvd. & WSU Spokane | Cincinnati St. & Springfield Ave. | Wall St.

Completed Stations Phase I

Station railings are being installed at the stations that have been completed in Phase I of construction.

Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Curbing
  • Landscaping
  • Seat wall construction

Construction at this location is planned to be completed in July. View the traffic control plan here.

Cincinnati Street & Springfield Avenue – City Line Station 20

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Sidewalks
  • Driveway approaches
  • Landscaping
  • Roadway grading
  • Fire hydrant replacement

Construction at this location is planned to be completed in August. View the traffic control plan here.

Wall Street Roadwork – between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Traffic control installation
  • Tree removal
  • Electrical disconnects
  • Pothole work
  • Demolition work

Construction at this location is planned to be completed in November. View the traffic control plan here.

July 15 - July 22

Spokane Falls Blvd. & WSU Spokane | Cincinnati St. & Springfield Ave. | Wall St.

Station Railing Installation

Station railings are being installed at the completed stations.

Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Sidewalk and sidewalk wall construction
  • Asphalt Paving

Construction at this location is planned to be completed in July. View the traffic control plan here.

Cincinnati Street & Springfield Avenue – City Line Station 20

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Storm drainage
  • Roadway grading
  • Concrete prep work
  • Curbing
  • Fire hydrant replacement at the northeast corner of Cincinnati and Springfield

Construction at this location is planned to be completed in August. View the traffic control plan here.

Wall Street Roadwork- between Riverside Avenue and Main Avenue 

Work includes road improvements to prepare the street for use by a 60′ City Line vehicle. 

  • Road closures beginning July 19
  • Surveying and other pre construction work

Construction at this location is planned to be completed in November. View the traffic control plan here.

July 8 - July 15

Cincinnati St. & Springfield Ave. | Spokane Falls Blvd. & WSU Spokane

Station Railing Installation

Station railings are being installed at the completed stations.

Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Curbing and bus pad concrete

Construction at this location is planned to be completed in July. View the traffic control plan here.

Cincinnati Street & Springfield Avenue – City Line Station 20

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Storm drainage
  • Roadway grading
  • Concrete prep work
  • Electrical conduit installation
  • Driveway installation

Construction at this location is planned to be completed in August. View the traffic control plan here.

July 1 - July 8

Cincinnati St. & Springfield Ave. | Spokane Falls Blvd. & WSU Spokane

Station Railing Installation

Station railings are being installed at the completed stations.

Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Concrete prep work
  • Curbing and bus pad concrete

Construction at this location is planned to be completed in July. View the traffic control plan here.

Cincinnati Street & Springfield Avenue – City Line Station 20

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Storm drainage
  • Roadway grading
  • Concrete prep work
  • Electrical conduit installation
  • Driveway installation

Construction at this location is planned to be completed in August. View the traffic control plan here.

June 24 - July 1

Cincinnati St. & Sharp Ave. | Cincinnati St. & Springfield Ave. | Spokane Falls Blvd. & WSU Spokane | Main Ave. & Bernard St. 

Main Avenue & Bernard Street – City Line Station 14

Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.

  • Sidewalk and street gutter installation
  • Platform concrete

Construction at this location is planned to be completed in June. View the traffic control plan here.

Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Electrical conduit
  • Seat walls

Construction at this location is planned to be completed in July. View the traffic control plan here.

Cincinnati Street & Springfield Avenue – City Line Station 20

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Demolition work
  • Driveway work

Construction at this location is planned to be completed in August. View the traffic control plan here.

Cincinnati Street & Sharp Avenue – City Line Road Work

Work includes repairs to the light pole base at the intersection.

  • Light pole installation 

Construction at this location is planned to be completed in late June.

June 17 - June 24

Cincinnati St. & Sharp Ave. | Cincinnati St. & Springfield Ave. | Cincinnati St. & Mission Ave. | Spokane Falls Blvd. & WSU Spokane | Main Ave. & Bernard St. | Sprague Ave. & Wall St. 

Sprague Avenue & Wall Street – City Line Station 11

Work includes foundations for City Line amenities and ADA improvements.

  • Sign installation
  • Striping 

Construction at this location is planned to be completed in June. View the traffic control plan here.

Main Avenue & Bernard Street – City Line Station 14

Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.

  • Footings
  • Sidewalk

Construction at this location is planned to be completed in June. View the traffic control plan here.

Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Waterline
  • Storm drainage
  • Subgrade preparation
  • Electrical conduit

Construction at this location is planned to be completed in July. View the traffic control plan here.

Cincinnati Street & Springfield Avenue – City Line Station 20

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Demolition work

Construction at this location is planned to be completed in August. View the traffic control plan here.

Cincinnati Street & Mission Avenue – City Line Road Work

Work includes repairs and traffic signal installation at the intersection.

  • Traffic signal installation

Construction at this location is planned to be completed in June 18. View the traffic control plan here.

Cincinnati Street & Sharp Avenue – City Line Road Work

Work includes repairs to the light pole base at the intersection.

  • Light pole base repair

Construction at this location is planned to be completed in late June.

June 10 - June 17

Cincinnati St. & Mission Ave. | Spokane Falls Blvd. & WSU Spokane | Main Ave. & Bernard St. | Sprague Ave. & Wall St. 

Sprague Avenue & Wall Street – City Line Station 11

Work includes foundations for City Line amenities and ADA improvements.

  • Sidewalks
  • Footings
  • Platform

Construction at this location is planned to be completed in June. View the traffic control plan here.

Main Avenue & Bernard Street – City Line Station 14

Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.

  • Curbing
  • Footings

Construction at this location is planned to be completed in June. View the traffic control plan here.

Spokane Falls Blvd at WSU Spokane – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Waterline
  • Storm drainage
  • Subgrade preparation
  • Electrical conduit

Construction at this location is planned to be completed in July. View the traffic control plan here.W

Cincinnati Street & Mission Avenue – City Line Road Work

Work includes repairs and traffic signal installation at the intersection.

  • Light pole base replacement
  • Traffic signal installation

Construction at this location is planned to be completed in June 18. View the traffic control plan here.

June 3 - June 10

Spokane Falls Blvd. & WSU Spokane | Main Ave. & Bernard St. | Sprague Ave. & Wall St. | Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St. 

Pacific Avenue & Hemlock Street – City Line Station 3

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Landscaping
  • Striping and sign installation
  • Final cleanup

Construction at this location is planned to be completed in June. View the traffic control plan here.

Pacific Avenue & Oak Street – City Line Station 5

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Platform concrete
  • Landscaping
  • Striping and sign installation
  • Final cleanup

Construction at this location is planned to be completed in June. View the traffic control plan here.

Sprague Avenue & Wall Street – City Line Station 11

Work includes foundations for City Line amenities and ADA improvements.

  • Concrete curbing
  • Sidewalks

Construction at this location is planned to be completed in June. View the traffic control plan here.

Main Avenue & Bernard Street – City Line Station 14

Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.

  • Grading
  • Form for concrete bus pad

Construction at this location is planned to be completed in June. View the traffic control plan here.

Spokane Falls Blvd at WSU Spokane – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Demolition work

Construction at this location is planned to be completed in July. View the traffic control plan here.

May 27 - June 3

Main Ave. & Bernard St. | Sprague Ave. & Wall St. | First Ave. & Adams St. | Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St. 

Pacific Avenue & Hemlock Street – City Line Station 3

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Platform concrete
  • Landscaping

Construction at this location is planned to be completed in June. View the traffic control plan here.

Pacific Avenue & Oak Street – City Line Station 5

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Platform concrete
  • Foundation concrete
  • Landscaping

Construction at this location is planned to be completed in June. View the traffic control plan here.

First Avenue & Adams Street – City Line Station 6

Work includes utility improvements and paving on First Avenue to facilitate station installation.

  • Brick gutter construction

Construction at this location is planned to be completed in mid May. View the traffic control plan here.

Sprague Avenue & Wall Street – City Line Station 11

Work includes foundations for City Line amenities and ADA improvements.

  • Concrete curbing
  • Sidewalks

Construction at this location is planned to be completed in June. View the traffic control plan here.

Main Avenue & Bernard Street – City Line Station 14

Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.

  • Waterline work
  • Grading
  • Storm drainage

Construction at this location is planned to be completed in June. View the traffic control plan here.

Spokane Falls Blvd at WSU – City Line Station 19a/19b

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Sawcutting
  • Demolition work

Construction at this location is planned to be completed in July. View the traffic control plan here.

May 20 - May 27

Main Ave. & Bernard St. | Sprague Ave. & Wall St. | First Ave. & Adams St. | Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St. 

Pacific Avenue & Hemlock Street – City Line Station 3

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Foundation concrete
  • Asphalt paving

Construction at this location is planned to be completed in June. View the traffic control plan here.

Pacific Avenue & Oak Street – City Line Station 5

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Foundation concrete
  • Bus pad construction

Construction at this location is planned to be completed in June. View the traffic control plan here.

First Avenue & Adams Street – City Line Station 6

Work includes utility improvements and paving on First Avenue to facilitate station installation.

  • Brick gutter construction

Construction at this location is planned to be completed in mid May. View the traffic control plan here.

Sprague Avenue & Wall Street – City Line Station 11

Work includes foundations for City Line amenities and ADA improvements.

  • Utilities
  • Subgrade preparation
  • Concrete paving

Construction at this location is planned to be completed in June. View the traffic control plan here.

Main Avenue & Bernard Street – City Line Station 14

Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.

  • Electrical work
  • Water line work
  • Demolition

Construction at this location is planned to be completed in June. View the traffic control plan here.

May 13 - May 20

Main Ave. & Bernard St. | Main Ave. & Howard St. | Sprague Ave. & Wall St. | First Ave. & Adams St. | Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St. 

Pacific Avenue & Hemlock Street – City Line Station 3

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Platform curbing

Construction at this location is planned to be completed in June. View the traffic control plan here.

Pacific Avenue & Oak Street – City Line Station 5

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Street and platform curbing
  • Bus pad construction

Construction at this location is planned to be completed in June. View the traffic control plan here.

First Avenue & Adams Street – City Line Station 6

Work includes utility improvements and paving on First Avenue to facilitate station installation.

  • Brick gutter construction

Construction at this location is planned to be completed in mid May. View the traffic control plan here.

Sprague Avenue & Wall Street – City Line Station 11

Work includes foundations for City Line amenities and ADA improvements.

  • Demolition work
  • Utility work

Construction at this location is planned to be completed in June. View the traffic control plan here.

Main Avenue & Howard Street – City Line Station 12

Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.

  • Tree well work
  • Striping

Construction at this location is planned to be completed in June. View the traffic control plan here.

Main Avenue & Bernard Street – City Line Station 14

Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.

  • Demolition work
  • Waterline work

Construction at this location is planned to be completed in June. View the traffic control plan here.

May 6 - May 13

Mission Ave. & Cincinnati St. | Sprague Ave. & Wall St. | First Ave. & Adams St. | Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St. | Main Ave. & Howard St. 

Cincinnati Street & Mission Avenue – City Line Road Work

Work includes road and traffic signal improvements at the intersection of Cincinnati Street and Mission Avenue to accommodate City Line buses.

  • Demolition work
  • Traffic signal work
  • Paving

The intersection closure is planned to be completed by May 14. View the traffic control plan here.

Pacific Avenue & Hemlock Street – City Line Station 3

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Bus pad construction
  • Platform curbing

Construction at this location is planned to be completed in June. View the traffic control plan here.

Pacific Avenue & Oak Street – City Line Station 5

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Bus pad construction
  • Platform curbing

Construction at this location is planned to be completed in June. View the traffic control plan here.

First Avenue & Adams Street – City Line Station 6

Work includes utility improvements and paving on First Avenue to facilitate station installation.

  • Demolition work
  • Paving

Construction at this location is planned to be completed in mid May. View the traffic control plan here.

Sprague Avenue & Wall Street – City Line Station 11

Work includes foundations for City Line amenities and ADA improvements.

  • Demolition work

Construction at this location is planned to be completed in June. View the traffic control plan here.

Main Avenue & Howard Street – City Line Station 12

Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.

  • Gutter work
  • Platform concrete

Construction at this location is planned to be completed in June. View the traffic control plan here.

April 30 - May 6

Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St. | Main Ave. & Howard St. 

Pacific Avenue & Oak Street – City Line Station 5

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Demolition work

Construction at this location is planned to be completed in June. View the traffic control plan here.

Pacific Avenue & Hemlock Street – City Line Station 3

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Roadway grading
  • Storm drain piping
  • Waterline

Construction at this location is planned to be completed in June. View the traffic control plan here.

Main Avenue & Howard Street – City Line Station 12

Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.

  • Platform footings
  • Sidewalk

Construction at this location is planned to be completed in June. View the traffic control plan here.

April 23 - April 30

Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St. | Main Ave. & Howard St. | First Ave. & Monroe St. | Sprague Ave. & Monroe St.

Pacific Avenue & Oak Street – City Line Station 5

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Demolition work

Construction at this location is planned to be completed in June. View the traffic control plan here.

Pacific Avenue & Hemlock Street – City Line Station 3

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Roadway grading
  • Storm drain piping
  • Waterline

Construction at this location is planned to be completed in June. View the traffic control plan here.

Main Avenue & Howard Street – City Line Station 12

Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.

  • Platform footings
  • Sidewalk

Construction at this location is planned to be completed in June. View the traffic control plan here.

First Avenue & Monroe Street – City Line Station 8

Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.

  • Signs and striping

Sprague Avenue & Monroe Street – City Line Station 9

Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.

  • Signs and striping

April 16 - April 23

Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St. | Main Ave. & Howard St. | First Ave. & Monroe St. | Sprague Ave. & Monroe St. | Maple St. & Pacific Ave.

Pacific Avenue & Oak Street – City Line Station 5

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Demolition work
  • Tree trimming

Construction at this location is planned to be completed in June. View the traffic control plan here.

Pacific Avenue & Hemlock Street – City Line Station 3

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Demolition work
  • Storm drainage

Construction at this location is planned to be completed in June. View the traffic control plan here.

Main Avenue & Howard Street – City Line Station 12

Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.

  • Demolition work
  • Bus pad construction

Construction at this location is planned to be completed in June. View the traffic control plan here.

First Avenue & Monroe Street – City Line Station 8

Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.

  • Paving complete
  • Platform and sidewalk concrete

Construction at this location is planned to be completed in late-April. View the traffic control plan here.

Sprague Avenue & Monroe Street – City Line Station 9

Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.

  • Street paving complete
  • Final sidewalk paving

Construction at this location is planned to be completed in late-April. View the traffic control plan here.

 

Maple Street & Pacific Avenue – Roadway Improvements

Work includes a public transit-rated roadway, pedestrian improvements, and new up-sized City waterline and stormwater improvements.

  • Roadway open
  • Paving complete
  • Avista pole installation

April 9 - April 16

Pacific Ave. & Hemlock St. | Main Ave. & Howard St. | First Ave. & Monroe St. | Sprague Ave. & Monroe St. | Maple St. & Pacific Ave.

Pacific Avenue & Hemlock Street – City Line Station 3

Work includes foundations for City Line amenities, ADA improvements and landscape improvements.

  • Intersection closure April 15 – June
  • Traffic Control

Construction at this location is planned to be completed in June. View the traffic control plan here.

Main Avenue & Howard Street – City Line Station 12

Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.

  • City waterline construction
  • Demolition work
  • Bus pad construction

Construction at this location is planned to be completed in June. View the traffic control plan here.

First Avenue & Monroe Street – City Line Station 8

Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.

  • Bus pad
  • Curbing
  • Foundation construction
  • Platform construction
  • Paving

Construction at this location is planned to be completed in late-April. View the traffic control plan here.

Sprague Avenue & Monroe Street – City Line Station 9

Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.

  • Foundation construction
  • Platform construction
  • Paving

Construction at this location is planned to be completed in late-April. View the traffic control plan here.

 

Maple Street & Pacific Avenue – Roadway Improvements

Work includes a public transit-rated roadway, pedestrian improvements, and new up-sized City waterline and stormwater improvements.

  • Final grading of subgrade
  • Paving
  • Construct center island

Construction at this location is planned to be completed in mid-April. View the traffic control plan here.

April 2 - April 9

Main Ave. & Howard St. | First Ave. & Monroe St. | Sprague Ave. & Monroe St. | Maple St. & Pacific Ave.

Main Avenue & Howard Street – City Line Station 12

Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.

  • Demolition work

Construction at this location is planned to be completed in June. View the traffic control plan here.

First Avenue & Monroe Street – City Line Station 8

Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.

  • Finalize waterline work
  • Pour bus pad
  • Curb preparation

Construction at this location is planned to be completed in late-April. View the traffic control plan here.

Sprague Avenue & Monroe Street – City Line Station 9

Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.

  • Foundation curbing
  • Platform curbing

Construction at this location is planned to be completed in late-April. View the traffic control plan here.

 

Maple Street & Pacific Avenue – Roadway Improvements

Work includes a public transit-rated roadway, pedestrian improvements, and new up-sized City waterline and stormwater improvements.

  • Grading of subgrade

Construction at this location is planned to be completed in mid-April. View the traffic control plan here.

MArch 26 - April 2

First Ave. & Monroe St. | Sprague Ave. & Monroe St. | Maple St. & Pacific Ave.

First Avenue & Monroe Street – City Line Station 8

Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.

  • Demolition work on First Avenue
  • Waterline work

Construction at this location is planned to be completed in late-April. View the traffic control plan here.

Sprague Avenue & Monroe Street – City Line Station 9

Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.

  • Bus platform construction
  • Roadway grading
  • Irrigation conduit behind platform

Construction at this location is planned to be completed in late-April. View the traffic control plan here.

 

Maple Street & Pacific Avenue – Roadway Improvements

Work includes a public transit-rated roadway, pedestrian improvements, and new up-sized City waterline and stormwater improvements.

  • Curb and sidewalk work
  • Grading of subgrade

Construction at this location is planned to be completed in mid-April. View the traffic control plan here.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

MArch 19-26

First Ave. & Monroe St.  | Sprague Ave. & Monroe St.  |  Maple St. & Pacific ave.

First Avenue & Monroe Street – City Line Station 8

Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.

  • March 22 construction start
  • Demolition work on First Avenue
  • Waterline work

Construction at this location is planned to be completed in late-April. View the traffic control plan here.

Sprague Avenue & Monroe Street – City Line Station 9

Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.

  • Light pole moved
  • Utility work
  • Roadway grading

Construction at this location is planned to be completed in late-April. View the traffic control plan here.

 

Maple Street & Pacific Avenue – Roadway Improvements

Work includes a public transit-rated roadway, pedestrian improvements, and new up-sized City waterline and stormwater improvements.

  • Final storm and sewer work
  • Curb and sidewalk work

Construction at this location is planned to be completed in mid-April. View the traffic control plan here.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

MArch 12-19

Sprague Avenue & Monroe Street  |  Maple Street & Pacific avenue

Sprague Avenue & Monroe Street – City Line Station 9

Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.

  • Southern two lanes of Sprague Avenue closed between Monroe Street and Madison Street March 15 to April
  • Utility and roadway work in preparation for a City Line station

Construction at this location is planned to be completed in late-April. View the traffic control plan here.

 

Maple Street & Pacific Avenue – Roadway Improvements

Work includes a public transit-rated roadway, pedestrian improvements, and new up-sized City waterline and stormwater improvements.

  • Waterline install, pressure test and bacteria test
  • Run new water services
  • Storm water and sewer work

Construction at this location is planned to be completed in mid-April. View the traffic control plan here.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

MArch 5-12

Pedestrian & Road Improvements ‐ Maple Street & Pacific Avenue 

  • Utility work including the setting of a new manhole and trenching for new waterlines
  • Installation of waterlines, valves and services
  • Waterline pressure test and chlorination
  • Graded roadway to subgrade

Construction at this location is planned to be completed in mid-April. View the traffic control plan here.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

February 26 - March 5

Pedestrian & Road Improvements ‐ Maple Street & Pacific Avenue 

  • Construction of pedestrian and road improvements for City Line at the intersection of South Maple Street and West Pacific Avenue.
  • Demolition of asphalt, curbing, and sidewalk, roadway grating, and preparation for water and sewer utility work. 

Construction at this location is planned to be completed in mid-April. View the traffic control plan here.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

February 22-26

Pedestrian & Road Improvements ‐ Maple Street & Pacific Avenue 

A full closure of the intersection of South Maple Street and West Pacific Avenue was put in place to accommodate utility work on Feb 22.

South Maple Street is closed from West 1st Avenue to Pacific Avenue and Pacific Avenue is closed from South Oak Street to South Maple Street. Pacific Avenue is also closed to thru traffic from South Cannon Street to South Oak Street.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

City Line road improvement construction begins at the same location on March 1 and is planned to be completed in mid-April.

This work will reconstruct the roadway. Benefits include a public transit-rated roadway, pedestrian improvements, and new up-sized City waterline and stormwater improvements.

Detour and construction signage are in place around the road closures and bus routes 60 and 61 are affected. Temporary bus stops are located at West 2nd Avenue and South Oak Street as well as West 2nd Avenue and South Chestnut Street, in place of stops along Pacific that are closed during construction. Visit SpokaneTransit.com for details. 

The illustrations in the renderings are a conceptual representation of a City Line station. Some elements are subject to change pending the remaining design work.