Construction updates


October 28- November 4
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan
Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan
Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan
Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan
Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan
Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan
Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan
Station 14 Main and Bernard Eastbound. September 30 to November.
Station 15 at Riverside and Bernard Westbound. August 2 to September. Traffic Control Plan
Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan
Station 18 at Main and Pines. August 29 to October. Traffic Control Plan
Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.
Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.
Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan
Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.
Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.
Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan
Station 28 at Spokane Community College. September 1 to October.


October 21- October 28
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan
Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan
Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan
Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan
Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan
Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan
Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan
Station 14 Main and Bernard Eastbound. September 30 to November.
Station 15 at Riverside and Bernard Westbound. August 2 to September. Traffic Control Plan
Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan
Station 18 at Main and Pines. August 29 to October. Traffic Control Plan
Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.
Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.
Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan
Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.
Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.
Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan
Station 28 at Spokane Community College. September 1 to October.




October 14 - October 21
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan
Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan
Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan
Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan
Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan
Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan
Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan
Station 14 Main and Bernard Eastbound. September 30 to November.
Station 15 at Riverside and Bernard Westbound. August 2 to September. Traffic Control Plan
Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan
Station 18 at Main and Pines. August 29 to October. Traffic Control Plan
Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.
Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.
Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan
Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.
Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.
Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan
Station 28 at Spokane Community College. September 1 to October.



October 7 - October 14
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan
Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan
Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan
Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan
Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan
Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan
Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan
Station 14 Main and Bernard Eastbound. September 30 to November.
Station 15 at Riverside and Bernard Westbound. August 2 to September. Traffic Control Plan
Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan
Station 18 at Main and Pines. August 29 to October. Traffic Control Plan
Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.
Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.
Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan
Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.
Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.
Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan
Station 28 at Spokane Community College. September 1 to October.




September 30 - October 7
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan
Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan
Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan
Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan
Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan
Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan
Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan
Station 14 Main and Bernard Eastbound. September 30 to November.
Station 15 at Riverside and Bernard Westbound. August 2 to September. Traffic Control Plan
Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan
Station 18 at Main and Pines. August 29 to October. Traffic Control Plan
Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.
Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.
Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan
Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.
Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.
Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan
Station 28 at Spokane Community College. September 1 to October.




September 23 - September 30
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to September. Traffic Control Plan
Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan
Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan
Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan
Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan
Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan
Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan
Station 15 at Riverside and Bernard Westbound. August 2 to September. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to September. Traffic Control Plan
Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan
Station 18 at Main and Pines. August 29 to October. Traffic Control Plan
Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.
Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.
Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan
Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.
Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.
Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan
Station 23 at Mission and Perry Eastbound. June 13 to September. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to September. Traffic Control Plan
Station 28 at Spokane Community College. September 1 to October.


September 16 - September 23
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 23 at Mission and Perry Eastbound. June 13 to September. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to September. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to September. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to September. Traffic Control Plan
Station 26b at Mission & Cook & 27b at Mission & Regal Eastbound July 19 to September. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to September. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to September. Traffic Control Plan
Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan
Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan
Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan
Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan
Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan
Station 15 at Riverside and Bernard Westbound. August 2 to September. Traffic Control Plan
Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan
Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan
Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan
Station 18 at Main and Pines. August 29 to October. Traffic Control Plan
Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan
Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan
Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.
Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.
Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.
Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.
Station 28 at Spokane Community College. September 1 to October.


September 9 - September 16
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 23 at Mission and Perry Eastbound. June 13 to September. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to September. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to September. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to September. Traffic Control Plan
Station 26b at Mission & Cook & 27b at Mission & Regal Eastbound July 19 to September. Traffic Control Plan
Station 27b at Mission and Regal Eastbound. June 6 to September. Traffic Control Plan
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to September. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to September. Traffic Control Plan
Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan
Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan
Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan
Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan
Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan
Station 15 at Riverside and Bernard Westbound. August 2 to September. Traffic Control Plan
Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan
Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan
Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan
Station 18 at Main and Pines. August 29 to October. Traffic Control Plan
Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan
Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan
Station 28 at Spokane Community College. September 1 to October.


September 2 - September 9
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 23 at Mission and Perry Eastbound. June 13 to September. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to September. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to September. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to September. Traffic Control Plan
Station 26b at Mission & Cook & 27b at Mission & Regal Eastbound July 19 to September. Traffic Control Plan
Station 27b at Mission and Regal Eastbound. June 6 to September. Traffic Control Plan
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to September. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to September. Traffic Control Plan
Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan
Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan
Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan
Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan
Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan
Station 15 at Riverside and Bernard Westbound. August 2 to September. Traffic Control Plan
Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan
Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan
Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan
Station 18 at Main and Pines. August 29 to October. Traffic Control Plan
Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan
Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan
Station 28 at Spokane Community College. September 1 to October.


August 26 - September 2
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 23 at Mission and Perry Eastbound. June 13 to September. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to September. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to September. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to September. Traffic Control Plan
Station 26b at Mission & Cook & 27b at Mission & Regal Eastbound July 19 to September. Traffic Control Plan
Station 27b at Mission and Regal Eastbound. June 6 to September. Traffic Control Plan
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to September. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to September. Traffic Control Plan
Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan
Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan
Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan
Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan
Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan
Station 15 at Riverside and Bernard Westbound. August 2 to September. Traffic Control Plan
Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan
Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan
Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan
Station 18 at Main and Pines. August 29 to October. Traffic Control Plan
Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan
Station 22 at Mission and Columbus. September 5 to October.


August 19 - August 26
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 23 at Mission and Perry Eastbound. June 13 to August. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to August. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to August. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to August. Traffic Control Plan
Station 26b at Mission & Cook & 27b at Mission & Regal Eastbound July 19 to August. Traffic Control Plan
Station 27b at Mission and Regal Eastbound. June 6 to August. Traffic Control Plan
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to August. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to August. Traffic Control Plan
Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan
Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan
Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan
Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan
Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan
Station 15 at Riverside and Bernard Westbound. August 2 to September. Traffic Control Plan
Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan
Station 12 at Main and Howard Eastbound. August 10 to September. Traffic Control Plan
Station 13 Riverside and Stevens Westbound. at August 9 to September. Traffic Control Plan


August 12 - August 19
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 23 at Mission and Perry Eastbound. June 13 to August. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to August. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to August. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to August. Traffic Control Plan
Station 26b at Mission & Cook & 27b at Mission & Regal Eastbound July 19 to August. Traffic Control Plan
Station 27b at Mission and Regal Eastbound. June 6 to August. Traffic Control Plan
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to August. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to August. Traffic Control Plan
Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan
Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan
Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan
Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan
Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan
Station 15 at Riverside and Bernard Westbound. August 2 to September. Traffic Control Plan
Station 17 at Riverside and Division Westbound. August 2 to September Traffic Control Plan
Station 12 at Main and Howard Eastbound. August 10 to September. Traffic Control Plan
Station 13 Riverside and Stevens Westbound. at August 9 to September. Traffic Control Plan


August 5 - August 12
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 23 at Mission and Perry Eastbound. June 13 to August. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to August. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to August. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to August. Traffic Control Plan
Station 26b at Mission & Cook & 27b at Mission & Regal Eastbound July 19 to August. Traffic Control Plan
Station 27b at Mission and Regal Eastbound. June 6 to August. Traffic Control Plan
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to August. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to August. Traffic Control Plan
Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan
Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan
Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan
Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan
Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan
Station 15 at Riverside and Bernard Westbound. August 2 to September. Traffic Control Plan
Station 17 at Riverside and Division Westbound. August 2 to September Traffic Control Plan
Station 19a at Spokane Falls and WSU. July 18 to August. Traffic Control Plan
Station 12 at Main and Howard Eastbound. August 10 to September. Traffic Control Plan
Station 13 Riverside and Stevens Westbound. at August 9 to September. Traffic Control Plan


July 29 - August 5
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 23 at Mission and Perry Eastbound. June 13 to August. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to August. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to August. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to August. Traffic Control Plan
Station 26b at Mission & Cook & 27b at Mission & Regal Eastbound July 19 to August. Traffic Control Plan
Station 27b at Mission and Regal Eastbound. June 6 to August. Traffic Control Plan
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to August. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to August. Traffic Control Plan
Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan
Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan
Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan
Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan
Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan
Station 15 at Riverside and Bernard Westbound. August 2 to September. Traffic Control Plan
Station 17 at Riverside and Division Westbound. August 2 to September Traffic Control Plan
Station 19a at Spokane Falls and WSU. July 18 to August. Traffic Control Plan


July 22 - July 29
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 19a at Spokane Falls and WSU. July 18 to August. Traffic Control Plan
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to August. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to August. Traffic Control Plan
Station 23 at Mission and Perry Eastbound. June 13 to August. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to August. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to August. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to August. Traffic Control Plan
Station 26b at Mission & Cook & 27b at Mission & Regal Eastbound July 19 to August. Traffic Control Plan


July 15 - July 22
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to August. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to August. Traffic Control Plan
Station 23 at Mission and Perry Eastbound. June 13 to August. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to August. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to August. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to August. Traffic Control Plan
Station 26b at Mission & Cook & 27b at Mission & Regal Eastbound July 19 to August. Traffic Control Plan


July 8 - July 15
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to August. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to August. Traffic Control Plan
Station 23 at Mission and Perry Eastbound. June 13 to August. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to August. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to August. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to August. Traffic Control Plan
Station 26b at Mission & Cook & 27b at Mission & Regal Eastbound July 19 to August. Traffic Control Plan


July 1 - July 8
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to August. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to August. Traffic Control Plan
Station 23 at Mission and Perry Eastbound. June 13 to August. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to August. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to August. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to August. Traffic Control Plan
Station 26b at Mission & Cook & 27b at Mission & Regal Eastbound July 5 to August. Traffic Control Plan


June 24 - July 1
Phase I of construction is substantially complete.
Phase II amenity installation has begun. Active construction locations include:
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to August. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to August. Traffic Control Plan
Station 23 at Mission and Perry Eastbound. June 13 to August. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to August. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to August. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to August. Traffic Control Plan


June 17 - June 24
Phase I of construction is substantially complete. Landscaping at stations is complete. Railing installation and painting at all stations is underway.
Phase II amenity installation has begun. Active construction locations include:
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to August. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to August. Traffic Control Plan
Station 23 at Mission and Perry Eastbound. June 13 to August. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to August. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to August. Traffic Control Plan
Station 7 at Sprague & Adams Westbound June 20 to August. Traffic Control Plan


June 10 - June 17
Phase I of construction is substantially complete. Landscaping at stations is complete. Railing installation and painting at all stations is underway.
Phase II amenity installation has begun. Active construction locations include:
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to August. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan
Station 24 at Mission and Perry Westbound. June 13 to August. Traffic Control Plan
Station 23 at Mission and Perry Eastbound. June 13 to August. Traffic Control Plan
Station 25b at Mission and Napa Eastbound. June 14 to August. Traffic Control Plan
Station 16 at Main & Division Eastbound June 16 to August. Traffic Control Plan


June 3 - June 10
Phase I of construction is substantially complete. Landscaping at stations is complete. Railing installation and painting at all stations is underway.
Phase II amenity installation has begun. Active construction locations include:
Station 27a at Mission and Regal Westbound. June 6 to August. Traffic Control Plan
Station 26a at Mission and Cook Westbound. June 7 to August. Traffic Control Plan
Station 25a at Mission and Napa Westbound. June 8 to August. Traffic Control Plan



May 27- June 3
Phase I of construction is substantially complete. Landscaping at stations is complete. Railing installation and painting at all stations is underway.
Phase II amenity installation will begin in June 6. Materials for amenities have arrived for installation.


May 20 - May 27
Phase I of construction is substantially complete. Railing installation, painting and landscaping at all stations will continue through August.
Phase II amenity installation will begin in June.


May 13 - May 20
Phase I of construction is substantially complete. Railing installation, painting and landscaping at all stations will continue through August.
Phase II amenity installation will begin in June.


April 29 - May 13
Mission Ave. at Columbus St. | Riverside Ave. at Bernard St. & Division St. | Riverside Ave. at Stevens St.
Riverside Avenue at Stevens Street – City Line Stations 13
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Temporary bus pad installation
- Bike lane installation
- Railing installation
Construction at this location is planned to be completed by May 1. View the Phase I traffic control plan here.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Bicycle lane installation
- Railing installation
Construction at this location is planned to be completed in March. View the Phase II traffic control plan here.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 22
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Installation of signalized RRFB (Rectangular Rapid Flashing Beacon) crosswalk
- ADA ramp installation
Construction at this location is planned to be completed by May.
- Railing Installation, Painting & Landscaping at All Stations – April
- Wall Street Landscaping and Brick Paver Placement – April


April 22 - April 29
Mission Ave. at Columbus St. | Riverside Ave. at Bernard St. & Division St. | Riverside Ave. at Stevens St.
Riverside Avenue at Stevens Street – City Line Stations 13
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Temporary bus pad installation
- Bike lane installation
- Railing installation
Construction at this location is planned to be completed by May 1. View the Phase I traffic control plan here.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Bicycle lane installation
- Railing installation
Construction at this location is planned to be completed in March. View the Phase II traffic control plan here.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 22
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Installation of signalized RRFB (Rectangular Rapid Flashing Beacon) crosswalk
- ADA ramp installation
Construction at this location is planned to be completed by May.
- Railing Installation, Painting & Landscaping at All Stations – April
- Wall Street Landscaping and Brick Paver Placement – April


April 15 - April 22
Mission Ave. at Columbus St. | Riverside Ave. at Bernard St. & Division St. | Riverside Ave. at Stevens St.
Riverside Avenue at Stevens Street – City Line Stations 13
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Concrete curb wall
- Concrete platform pour
Construction at this location is planned to be completed by May 1. View the Phase I traffic control plan here.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Concrete work in roadway
- Bicycle lane installation
Construction at this location is planned to be completed in March. View the Phase II traffic control plan here.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 22
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Installation of signalized RRFB (Rectangular Rapid Flashing Beacon) crosswalk
- ADA ramp installation
Construction at this location is planned to be completed by May.
- Railing Installation, Painting & Landscaping at All Stations – April
- Wall Street Landscaping and Brick Paver Placement – April


April 8 - April 15
Mission Ave. at Columbus St. | Riverside Ave. at Bernard St. & Division St. | Riverside Ave. at Stevens St.
Riverside Avenue at Stevens Street – City Line Stations 13
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Concrete bus pad
- Foundation concrete
Construction at this location is planned to be completed by May 1. View the Phase I traffic control plan here.C
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Railing installation
- Platform concrete
Construction at this location is planned to be completed in March. View the Phase II traffic control plan here.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 22
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- ADA ramp installation
- Electrical conduit installation
- Installation of a signalized crosswalk
Construction at this location is planned to be completed by May.
- Railing Painting & Landscaping at All Stations – April
- First Avenue & Adams Street – Station 6
- Sprague Avenue & Adams Street – Station 7
- Sprague Avenue & Monroe Street – Station 9


April 1 - April 8
Mission Ave. at Columbus St. | Riverside Ave. at Bernard St. & Division St. | Riverside Ave. at Stevens St.
Riverside Avenue at Stevens Street – City Line Stations 13
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Foundation concrete
Construction at this location is planned to be completed by May 1. View the Phase I traffic control plan here.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Railing installation
- Platform concrete
Construction at this location is planned to be completed in March. View the Phase II traffic control plan here.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 22
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- ADA ramp installation
- Electrical conduit installation
- Installation of a signalized crosswalk
Construction at this location is planned to be completed by May.
- Railing Painting & Landscaping at All Stations – April
- First Avenue & Adams Street – Station 6
- Sprague Avenue & Adams Street – Station 7
- Sprague Avenue & Monroe Street – Station 9


March 25 - April 1
Riverside Ave. at Bernard St. & Division St. | Riverside Ave. at Stevens St.
Riverside Avenue at Stevens Street – City Line Stations 13
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Foundation construction
Construction at this location is planned to be completed by May 1. View the Phase I traffic control plan here.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Handrail wall construction
- Platform concrete
Construction at this location is planned to be completed in March. View the Phase II traffic control plan here.
- Columbus Street and Mission Avenue Westbound – Station 22 – April
- Railing Painting & Landscaping at All Stations – April
- First Avenue & Adams Street – Station 6
- Sprague Avenue & Adams Street – Station 7
- Sprague Avenue & Monroe Street – Station 9


March 18 - March 25
Riverside Ave. at Bernard St. & Division St. | Riverside Ave. at Stevens St.
Riverside Avenue at Stevens Street – City Line Stations 13
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Demolition work.
Construction at this location is planned to be completed by May 1. View the Phase I traffic control plan here.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Curb installation
- Bike lane construction
- Platform concrete
Construction at this location is planned to be completed in March. View the Phase II traffic control plan here.
- Columbus Street and Mission Avenue Westbound – Station 22 – April
- First Avenue & Adams Street – Station 6
- Sprague Avenue & Adams Street – Station 7
- Sprague Avenue & Monroe Street – Station 9


March 4 - March 18
Riverside Ave. at Bernard St. & Division St. | Riverside Ave. at Stevens St.
Riverside Avenue at Stevens Street – City Line Stations 13
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Demolition work.
Construction at this location is planned to be completed by May 1. View the Phase I traffic control plan here.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Curb installation
- Bike lane construction
- Platform concrete
Construction at this location is planned to be completed in March. View the Phase II traffic control plan here.
- Columbus Street and Mission Avenue Westbound – Station 22


February 25 - March 4
Riverside Ave. at Bernard St. & Division St. | Riverside Ave. at Stevens St.
Riverside Avenue at Stevens Street – City Line Stations 13
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Demolition work.
Construction at this location is planned to be completed by May 1. View the Phase I traffic control plan here.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Final concrete work.
Construction at this location is planned to be completed in March. View the Phase II traffic control plan here.
- Columbus Street and Mission Avenue Westbound – Station 22


February 18 - February 25
Riverside Ave. at Bernard St. & Division St.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Final concrete work.
Construction at this location is planned to be completed in March. View the Phase II traffic control plan here.
- Stevens Street and Riverside Avenue – Station 13 on March 1
- Columbus Street and Mission Avenue Westbound – Station 22



February 11 - February 18
Riverside Ave. at Bernard St. & Division St.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Final concrete work.
Construction at this location is planned to be completed in March. View the Phase I traffic control plan here.
- Columbus Street and Mission Avenue Westbound – Station 22
- Stevens Street and Riverside Avenue – Station 13



January 21 - February
- Riverside Avenue at Bernard Street and Division Street – Stations 15 & 17
- Columbus Street and Mission Avenue Westbound – Station 22
- Stevens Street and Riverside Avenue – Station 13


January 14 - January 21
Riverside Ave. at Bernard St. & Division St.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Forming platform for concrete and roadway for bicycle lane installation
Construction at this location is planned to be completed in 2022. View the Phase I traffic control plan here. View the Phase II traffic control plan here.
- Riverside Avenue at Bernard Street and Division Street – Stations 15 & 17
- Columbus Street and Mission Avenue Westbound – Station 22
- Stevens Street and Riverside Avenue – Station 13



January 1 - January 14
Riverside Ave. at Bernard St. & Division St.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Curb concrete
- Platform concrete
Construction at this location is planned to be completed in 2022. View the Phase I traffic control plan here. View the Phase II traffic control plan here.
- Riverside Avenue at Bernard Street and Division Street – Stations 15 & 17
- Columbus Street and Mission Avenue Westbound – Station 22
- Stevens Street and Riverside Avenue – Station 13
December 24 - December 31
Riverside Ave. at Bernard St. & Division St.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Curb concrete
- Platform concrete
Construction at this location is planned to be completed in 2022. View the Phase I traffic control plan here. View the Phase II traffic control plan here.
- Riverside Avenue at Bernard Street and Division Street – Stations 15 & 17
- Columbus Street and Mission Avenue Westbound – Station 22
- Stevens Street and Riverside Avenue – Station 13
December 17 - December 24
Riverside Ave. at Bernard St. & Division St. | Wall St.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Curb installation
- Pour bus pad
Construction at this location is planned to be completed in 2022. View the Phase I traffic control plan here. View the Phase II traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Prep roadway for reopening
Construction at this location is planned to be completed in December. View the traffic control plan here.
- Riverside Avenue at Bernard Street and Division Street – Stations 15 & 17
- Columbus Street and Mission Avenue Westbound – Station 22
- Stevens Street and Riverside Avenue – Station 13
December 10 - December 17
Riverside Ave. at Bernard St. & Division St. | Wall St.
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Curb installation
Construction at this location is planned to be completed in 2022. View the Phase I traffic control plan here. View the Phase II traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Tile finishing
- Brick placement
Construction at this location is planned to be completed in December. View the traffic control plan here.
- Riverside Avenue at Bernard Street and Division Street – Stations 15 & 17
- Columbus Street and Mission Avenue Westbound – Station 22
- Stevens Street and Riverside Avenue – Station 13
December 3 - December 10
Riverside Ave. at Bernard St. & Division St. | Wall St.
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Curb installation
Construction at this location is planned to be completed in 2022. View the Phase I traffic control plan here. View the Phase II traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Tile finishing
- Brick placement
Construction at this location is planned to be completed in December. View the traffic control plan here.
November 26 - December 3
Riverside Ave. at Bernard St. & Division St. | Columbus St. & Mission Ave. | Wall St. | Mission Ave. & Perry St. Westbound
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Excavation and preparation for foundations and walls
- Electrical conduit installation
Construction at this location is planned to be completed in 2022. View the Phase I traffic control plan here. View the Phase II traffic control plan here.
Columbus Street and Mission Avenue Westbound – City Line Station 22
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Final construction clean up
Construction at this location is planned to be completed in November. View the Left Lane traffic control plan here. View the Right Lane traffic control plan here.
Perry Street and Mission Avenue Westbound – City Line Station 24
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Sidewalk installation
Construction at this location is planned to be completed in October. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Tile finishing
- Brick placement
Construction at this location is planned to be completed in December. View the traffic control plan here.
November 19 - November 26
Riverside Ave. at Bernard St. & Division St. | Columbus St. & Mission Ave. | Wall St. | Mission Ave. & Perry St. Westbound
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Bus pad grading
- Stormwater drains
Construction at this location is planned to be completed in 2022. View the Phase I traffic control plan here. View the Phase II traffic control plan here.
Columbus Street and Mission Avenue Westbound – City Line Station 22
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Final construction clean up
Construction at this location is planned to be completed in 2022. View the Left Lane traffic control plan here. View the Right Lane traffic control plan here.
Perry Street and Mission Avenue Westbound – City Line Station 24
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Sidewalk installation
Construction at this location is planned to be completed in October. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Tile finishing
- Brick placement
- Irrigation installation
Construction at this location is planned to be completed in December. View the traffic control plan here.
November 12 - November 19
Riverside Ave. at Bernard St. & Division St. | Columbus St. & Mission Ave. | Wall St. | Mission Ave. & Perry St. Westbound
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Storm drainage
Construction at this location is planned to be completed in 2022. View the Phase I traffic control plan here. View the Phase II traffic control plan here.
Columbus Street and Mission Avenue Westbound – City Line Station 22
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Platform concrete
Construction at this location is planned to be completed in 2022. View the Left Lane traffic control plan here. View the Right Lane traffic control plan here.
Perry Street and Mission Avenue Westbound – City Line Station 24
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Communication lines installed
Construction at this location is planned to be completed in October. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Tile placement
- Street paving
Construction at this location is planned to be completed in November. View the traffic control plan here.
November 5 - November 12
Riverside Ave. at Bernard St. & Division St. | Columbus St. & Mission Ave. | Wall St. | Mission Ave. & Perry St. Westbound
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Storm drainage
Construction at this location is planned to be completed in November. View the Phase I traffic control plan here. View the Phase II traffic control plan here.
Columbus Street and Mission Avenue Westbound – City Line Station 22
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Foundation concrete
Construction at this location is planned to be completed in October. View the Left Lane traffic control plan here. View the Right Lane traffic control plan here.
Perry Street and Mission Avenue Westbound – City Line Station 24
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Sidewalk concrete
Construction at this location is planned to be completed in October. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Tile placement
- Concrete work for alley entrances
Construction at this location is planned to be completed in November. View the traffic control plan here.
October 29 - November 5
Riverside Ave. at Bernard St. & Division St. | Columbus St. & Mission Ave. | Wall St. | Mission Ave. & Perry St. Westbound
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Storm drainage
Construction at this location is planned to be completed in November. View the Phase I traffic control plan here. View the Phase II traffic control plan here.
Columbus Street and Mission Avenue Westbound – City Line Station 22
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Electrical work
- Light pole bases
- Foundation concrete
Construction at this location is planned to be completed in October. View the Left Lane traffic control plan here. View the Right Lane traffic control plan here.
Perry Street and Mission Avenue Westbound – City Line Station 24
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Platform concrete
- Sidewalk concrete
Construction at this location is planned to be completed in October. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Tile grouting
- Curbing
Construction at this location is planned to be completed in November. View the traffic control plan here.
October 22 - October 29
Riverside Ave. at Bernard St. & Division St. | Columbus St. & Mission Ave. | Napa St. & Mission Ave. Westbound | Wall St. | Mission Ave. & Perry St. Westbound
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Avista vault work
Construction at this location is planned to be completed in November. View the Phase I traffic control plan here. View the Phase II traffic control plan here.
Columbus Street and Mission Avenue Westbound – City Line Station 22
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Curbing
- Bus platform
Construction at this location is planned to be completed in October. View the Left Lane traffic control plan here. View the Right Lane traffic control plan here.
Perry Street and Mission Avenue Westbound – City Line Station 24
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Platform installation
- Paving
Construction at this location is planned to be completed in October. View the traffic control plan here.
Napa Street and Mission Avenue Westbound – City Line Station 25a
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Paving
- Platform installation
- Landscaping
Construction at this location is planned to be completed in October. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Tile installation
- Curbing
Construction at this location is planned to be completed in November. View the traffic control plan here.
October 15 - October 22
Riverside Ave. at Bernard St. & Division St. | Columbus St. & Mission Ave. | Napa St. & Mission Ave. Westbound | Wall St. | Mission Ave. & Perry St. Westbound
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Riverside Avenue at Bernard Street and Division Street – City Line Stations 15 & 17
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Demolition
- Avista vault work
Construction at this location is planned to be completed in November. View the Phase I traffic control plan here. View the Phase II traffic control plan here.
Columbus Street and Mission Avenue Westbound – City Line Station 22
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Electrical conduit
- Concrete bus pads
- Curbing
Construction at this location is planned to be completed in October. View the Left Lane traffic control plan here. View the Right Lane traffic control plan here.
Perry Street and Mission Avenue Westbound – City Line Station 24
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Platform installation
- Sidewalks
Construction at this location is planned to be completed in October. View the traffic control plan here.
Napa Street and Mission Avenue Westbound – City Line Station 25a
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Concrete work
- Sign revision
Construction at this location is planned to be completed in October. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Tile installation
- Curbing
Construction at this location is planned to be completed in November. View the traffic control plan here.
October 8 - October 15
Columbus St. & Mission Ave. | Napa St. & Mission Ave. Westbound | Wall St. | Mission Ave. & Perry St. Westbound
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Columbus Street and Mission Avenue Westbound – City Line Station 22
Work includes foundations for City Line amenities, ADA improvements, and landscape improvements.
- Demolition work
- Concrete bus pad
Construction at this location is planned to be completed in October. View the Left Lane traffic control plan here. View the Right Lane traffic control plan here.
Perry Street and Mission Avenue Westbound – City Line Station 24
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Platform installation
- Sidewalks
Construction at this location is planned to be completed in October. View the traffic control plan here.
Napa Street and Mission Avenue Westbound – City Line Station 25a
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Driveway approach
- Concrete walkways
- Platform installation
Construction at this location is planned to be completed in October. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Tile installation
Construction at this location is planned to be completed in November. View the traffic control plan here.
October 1 - October 8
Cook St. & Mission Ave. Eastbound & Westbound | Napa St. & Mission Ave. Westbound | Wall St. | Mission Ave. & Perry St. Westbound
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Perry Street and Mission Avenue Westbound – City Line Station 24
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Curb installation
- Footing construction
- Platform construction
- Sidewalk installation
- Electrical installation
- Asphalt paving
Construction at this location is planned to be completed in October. View the traffic control plan here.
Napa Street and Mission Avenue Westbound – City Line Station 25a
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Driveway approach
- Concrete walkways
- Footing construction
- Electrical installation
- Asphalt paving
Construction at this location is planned to be completed in October. View the traffic control plan here.
Cook Street and Mission Avenue Westbound – City Line Station 26a
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Platform construction
Construction at this location is planned to be completed in October. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Tile installation
Construction at this location is planned to be completed in November. View the traffic control plan here.
September 23 - October 1
Cook St. & Mission Ave. Eastbound & Westbound | Napa St. & Mission Ave. Westbound | Wall St. | Mission Ave. & Perry St. Westbound
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Perry Street and Mission Avenue Westbound – City Line Station 24
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Demolition work
Construction at this location is planned to be completed in October. View the traffic control plan here.
Napa Street and Mission Avenue Westbound – City Line Station 25a
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Demolition work
Construction at this location is planned to be completed in October. View the traffic control plan here.
Cook Street and Mission Avenue Westbound – City Line Station 26a
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- City vault adjustment
- Asphalt paving
- platform construction
Construction at this location is planned to be completed in October. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Light pole installation
- Irrigation installation
Construction at this location is planned to be completed in November. View the traffic control plan here.
September 16 - September 23
Cook St. & Mission Ave. Eastbound | Napa St. & Mission Ave. Eastbound & Westbound | Wall St.
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Napa Street and Mission Avenue Westbound – City Line Station 25a
Work includes foundations for City Line amenities, ADA improvements, landscape improvements and signage improvements.
- Demolition work
Construction at this location is planned to be completed in September. View the traffic control plan here.
Napa Street and Mission Avenue Eastbound – City Line Station 25b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Platform construction
- Sidewalks
Construction at this location is planned to be completed in September. View the traffic control plan here.
Cook Street and Mission Avenue Westbound – City Line Station 26a
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Bus pad construction
- Electrical installation
- Curb installation
- Platform construction
Construction at this location is planned to be completed in October. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Light pole installation
Construction at this location is planned to be completed in November. View the traffic control plan here.
September 9 - September 16
Cook St. & Mission Ave. Eastbound | Napa St. & Mission Ave. Eastbound | Wall St.
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Cook Street and Mission Avenue Westbound – City Line Station 26a
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Demolition Work
Construction at this location is planned to be completed in October. View the traffic control plan here.
Napa Street and Mission Avenue Eastbound – City Line Station 25b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Sidewalk repoured
- Footings install
- Electrical conduit install
Construction at this location is planned to be completed in September. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Light pole base installation
- Irrigation installation
Construction at this location is planned to be completed in November. View the traffic control plan here.
September 3 - September 9
Spokane Falls Blvd. & WSU Spokane | Cook St. & Mission Ave. Eastbound | Napa St. & Mission Ave. Eastbound | Wall St.
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Curb installation
- Landscaping work
- Striping and signing
- Construction clean up
Construction at this location is planned to be completed in August. View the traffic control plan here.
Cook Street & Mission Avenue Eastbound – City Line Station 26b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Electrical & communications installation
- Backfill around footings
- Platform concrete pour
- Street paving
Construction at this location is planned to be completed in September. View the traffic control plan here.
Napa Street and Mission Avenue Eastbound – City Line Station 25b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Gas line intallation
- Electrical installation
- Bus pad concrete pour
Construction at this location is planned to be completed in September. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Light pole base installation
- Work on tree wells
Construction at this location is planned to be completed in November. View the traffic control plan here.
August 27 - September 3
Spokane Falls Blvd. & WSU Spokane | Cook St. & Mission Ave. Eastbound | Napa St. & Mission Ave. Eastbound | Wall St.
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Curb installation
- Landscaping work
- Construction clean up
Construction at this location is planned to be completed in August. View the traffic control plan here.
Cook Street & Mission Avenue Eastbound – City Line Station 26b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Electrical & communications installation
- Backfill around footings
- Platform concrete pour
Construction at this location is planned to be completed in September. View the traffic control plan here.
Napa Street and Mission Avenue Eastbound – City Line Station 25b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Electrical installation
- Bus pad concrete pour
Construction at this location is planned to be completed in September. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Light pole base installation
- Work on tree wells
Construction at this location is planned to be completed in November. View the traffic control plan here.
August 20 -August 27
Spokane Falls Blvd. & WSU Spokane | Cincinnati St. & Springfield Ave. | Cook St. & Mission Ave. Eastbound | Napa St. & Mission Ave. Eastbound | Wall St.
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Heated platform pipe installation
- Platform concrete
- Curbing and landscaping
Construction at this location is planned to be completed in August. View the traffic control plan here.
Cincinnati Street & Springfield Avenue – City Line Station 20
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Sign installation
- Striping
- Cleanup
Construction at this location is planned to be completed in August. View the traffic control plan here.
Cook Street & Mission Avenue Eastbound – City Line Station 26b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Bus pad construction
- Curbing
- Electrical installation
Construction at this location is planned to be completed in September. View the traffic control plan here.
Napa Street and Mission Avenue Eastbound – City Line Station 25b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Demolition work
Construction at this location is planned to be completed in September. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Electrical conduit installation
- Tile removal continues
Construction at this location is planned to be completed in November. View the traffic control plan here.
August 13 -August 20
Spokane Falls Blvd. & WSU Spokane | Cincinnati St. & Springfield Ave. | Cook St. & Mission Ave. Eastbound | Wall St.
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Landscaping
- Sidewalk construction
- Footing construction
Construction at this location is planned to be completed in August. View the traffic control plan here.
Cincinnati Street & Springfield Avenue – City Line Station 20
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Landscaping
- Platform concrete
Construction at this location is planned to be completed in August. View the traffic control plan here.
Cook Street & Mission Avenue Eastbound – City Line Station 26b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Tree trimming
- Demolition
Construction at this location is planned to be completed in September. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Electrical conduit installation
- Tile removal continues
Construction at this location is planned to be completed in November. View the traffic control plan here.
Upcoming Projects:
- Station 25b at Mission Avenue and Napa Street eastbound is scheduled to begin construction Aug 25.
- Station 26a at Mission Avenue and Cook Street wesbound is scheduled to begin construction Sept 6.
Upcoming Projects:
- Station 25b at Mission Avenue and Napa Street eastbound is scheduled to begin construction Aug 25.
- Station 26a at Mission Avenue and Cook Street wesbound is scheduled to begin construction Sept 6.
August 6 -August 13
Spokane Falls Blvd. & WSU Spokane | Cincinnati St. & Springfield Ave. | Wall St.
Completed Stations Phase I
Railings are being installed at the stations that have been completed in Phase I of construction.
Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Landscaping
- Seat wall construction
- Sidewalk construction
- Footing construction
Construction at this location is planned to be completed in July. View the traffic control plan here.
Cincinnati Street & Springfield Avenue – City Line Station 20
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Landscaping
- Asphalt paving
- Entrance concrete construction
Construction at this location is planned to be completed in August. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Electrical conduit installation
- Tile removal
Construction at this location is planned to be completed in November. View the traffic control plan here.
July 29 - August 6
Spokane Falls Blvd. & WSU Spokane | Cincinnati St. & Springfield Ave. | Wall St.
Completed Stations Phase I
Station railings are being installed at the stations that have been completed in Phase I of construction.
Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Landscaping
- Seat wall construction
Construction at this location is planned to be completed in July. View the traffic control plan here.
Cincinnati Street & Springfield Avenue – City Line Station 20
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Sidewalks
- Landscaping
- Asphalt paving
Construction at this location is planned to be completed in August. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Electrical conduit installation
Construction at this location is planned to be completed in November. View the traffic control plan here.
July 22 - July 29
Spokane Falls Blvd. & WSU Spokane | Cincinnati St. & Springfield Ave. | Wall St.
Completed Stations Phase I
Station railings are being installed at the stations that have been completed in Phase I of construction.
Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Curbing
- Landscaping
- Seat wall construction
Construction at this location is planned to be completed in July. View the traffic control plan here.
Cincinnati Street & Springfield Avenue – City Line Station 20
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Sidewalks
- Driveway approaches
- Landscaping
- Roadway grading
- Fire hydrant replacement
Construction at this location is planned to be completed in August. View the traffic control plan here.
Wall Street Roadwork – between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Traffic control installation
- Tree removal
- Electrical disconnects
- Pothole work
- Demolition work
Construction at this location is planned to be completed in November. View the traffic control plan here.
July 15 - July 22
Spokane Falls Blvd. & WSU Spokane | Cincinnati St. & Springfield Ave. | Wall St.
Station Railing Installation
Station railings are being installed at the completed stations.
Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Sidewalk and sidewalk wall construction
- Asphalt Paving
Construction at this location is planned to be completed in July. View the traffic control plan here.
Cincinnati Street & Springfield Avenue – City Line Station 20
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Storm drainage
- Roadway grading
- Concrete prep work
- Curbing
- Fire hydrant replacement at the northeast corner of Cincinnati and Springfield
Construction at this location is planned to be completed in August. View the traffic control plan here.
Wall Street Roadwork- between Riverside Avenue and Main Avenue
Work includes road improvements to prepare the street for use by a 60′ City Line vehicle.
- Road closures beginning July 19
- Surveying and other pre construction work
Construction at this location is planned to be completed in November. View the traffic control plan here.
July 8 - July 15
Cincinnati St. & Springfield Ave. | Spokane Falls Blvd. & WSU Spokane
Station Railing Installation
Station railings are being installed at the completed stations.
Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Curbing and bus pad concrete
Construction at this location is planned to be completed in July. View the traffic control plan here.
Cincinnati Street & Springfield Avenue – City Line Station 20
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Storm drainage
- Roadway grading
- Concrete prep work
- Electrical conduit installation
- Driveway installation
Construction at this location is planned to be completed in August. View the traffic control plan here.
July 1 - July 8
Cincinnati St. & Springfield Ave. | Spokane Falls Blvd. & WSU Spokane
Station Railing Installation
Station railings are being installed at the completed stations.
Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Concrete prep work
- Curbing and bus pad concrete
Construction at this location is planned to be completed in July. View the traffic control plan here.
Cincinnati Street & Springfield Avenue – City Line Station 20
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Storm drainage
- Roadway grading
- Concrete prep work
- Electrical conduit installation
- Driveway installation
Construction at this location is planned to be completed in August. View the traffic control plan here.
June 24 - July 1
Cincinnati St. & Sharp Ave. | Cincinnati St. & Springfield Ave. | Spokane Falls Blvd. & WSU Spokane | Main Ave. & Bernard St.
Main Avenue & Bernard Street – City Line Station 14
Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.
- Sidewalk and street gutter installation
- Platform concrete
Construction at this location is planned to be completed in June. View the traffic control plan here.
Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Electrical conduit
- Seat walls
Construction at this location is planned to be completed in July. View the traffic control plan here.
Cincinnati Street & Springfield Avenue – City Line Station 20
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Demolition work
- Driveway work
Construction at this location is planned to be completed in August. View the traffic control plan here.
Cincinnati Street & Sharp Avenue – City Line Road Work
Work includes repairs to the light pole base at the intersection.
- Light pole installation
Construction at this location is planned to be completed in late June.
June 17 - June 24
Cincinnati St. & Sharp Ave. | Cincinnati St. & Springfield Ave. | Cincinnati St. & Mission Ave. | Spokane Falls Blvd. & WSU Spokane | Main Ave. & Bernard St. | Sprague Ave. & Wall St.
Sprague Avenue & Wall Street – City Line Station 11
Work includes foundations for City Line amenities and ADA improvements.
- Sign installation
- Striping
Construction at this location is planned to be completed in June. View the traffic control plan here.
Main Avenue & Bernard Street – City Line Station 14
Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.
- Footings
- Sidewalk
Construction at this location is planned to be completed in June. View the traffic control plan here.
Spokane Falls Boulevard at WSU Spokane – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Waterline
- Storm drainage
- Subgrade preparation
- Electrical conduit
Construction at this location is planned to be completed in July. View the traffic control plan here.
Cincinnati Street & Springfield Avenue – City Line Station 20
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Demolition work
Construction at this location is planned to be completed in August. View the traffic control plan here.
Cincinnati Street & Mission Avenue – City Line Road Work
Work includes repairs and traffic signal installation at the intersection.
- Traffic signal installation
Construction at this location is planned to be completed in June 18. View the traffic control plan here.
Cincinnati Street & Sharp Avenue – City Line Road Work
Work includes repairs to the light pole base at the intersection.
- Light pole base repair
Construction at this location is planned to be completed in late June.
June 10 - June 17
Cincinnati St. & Mission Ave. | Spokane Falls Blvd. & WSU Spokane | Main Ave. & Bernard St. | Sprague Ave. & Wall St.
Sprague Avenue & Wall Street – City Line Station 11
Work includes foundations for City Line amenities and ADA improvements.
- Sidewalks
- Footings
- Platform
Construction at this location is planned to be completed in June. View the traffic control plan here.
Main Avenue & Bernard Street – City Line Station 14
Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.
- Curbing
- Footings
Construction at this location is planned to be completed in June. View the traffic control plan here.
Spokane Falls Blvd at WSU Spokane – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Waterline
- Storm drainage
- Subgrade preparation
- Electrical conduit
Construction at this location is planned to be completed in July. View the traffic control plan here.W
Cincinnati Street & Mission Avenue – City Line Road Work
Work includes repairs and traffic signal installation at the intersection.
- Light pole base replacement
- Traffic signal installation
Construction at this location is planned to be completed in June 18. View the traffic control plan here.
June 3 - June 10
Spokane Falls Blvd. & WSU Spokane | Main Ave. & Bernard St. | Sprague Ave. & Wall St. | Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St.
Pacific Avenue & Hemlock Street – City Line Station 3
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Landscaping
- Striping and sign installation
- Final cleanup
Construction at this location is planned to be completed in June. View the traffic control plan here.
Pacific Avenue & Oak Street – City Line Station 5
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Platform concrete
- Landscaping
- Striping and sign installation
- Final cleanup
Construction at this location is planned to be completed in June. View the traffic control plan here.
Sprague Avenue & Wall Street – City Line Station 11
Work includes foundations for City Line amenities and ADA improvements.
- Concrete curbing
- Sidewalks
Construction at this location is planned to be completed in June. View the traffic control plan here.
Main Avenue & Bernard Street – City Line Station 14
Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.
- Grading
- Form for concrete bus pad
Construction at this location is planned to be completed in June. View the traffic control plan here.
Spokane Falls Blvd at WSU Spokane – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Demolition work
Construction at this location is planned to be completed in July. View the traffic control plan here.
May 27 - June 3
Main Ave. & Bernard St. | Sprague Ave. & Wall St. | First Ave. & Adams St. | Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St.
Pacific Avenue & Hemlock Street – City Line Station 3
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Platform concrete
- Landscaping
Construction at this location is planned to be completed in June. View the traffic control plan here.
Pacific Avenue & Oak Street – City Line Station 5
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Platform concrete
- Foundation concrete
- Landscaping
Construction at this location is planned to be completed in June. View the traffic control plan here.
First Avenue & Adams Street – City Line Station 6
Work includes utility improvements and paving on First Avenue to facilitate station installation.
- Brick gutter construction
Construction at this location is planned to be completed in mid May. View the traffic control plan here.
Sprague Avenue & Wall Street – City Line Station 11
Work includes foundations for City Line amenities and ADA improvements.
- Concrete curbing
- Sidewalks
Construction at this location is planned to be completed in June. View the traffic control plan here.
Main Avenue & Bernard Street – City Line Station 14
Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.
- Waterline work
- Grading
- Storm drainage
Construction at this location is planned to be completed in June. View the traffic control plan here.
Spokane Falls Blvd at WSU – City Line Station 19a/19b
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Sawcutting
- Demolition work
Construction at this location is planned to be completed in July. View the traffic control plan here.
May 20 - May 27
Main Ave. & Bernard St. | Sprague Ave. & Wall St. | First Ave. & Adams St. | Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St.
Pacific Avenue & Hemlock Street – City Line Station 3
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Foundation concrete
- Asphalt paving
Construction at this location is planned to be completed in June. View the traffic control plan here.
Pacific Avenue & Oak Street – City Line Station 5
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Foundation concrete
- Bus pad construction
Construction at this location is planned to be completed in June. View the traffic control plan here.
First Avenue & Adams Street – City Line Station 6
Work includes utility improvements and paving on First Avenue to facilitate station installation.
- Brick gutter construction
Construction at this location is planned to be completed in mid May. View the traffic control plan here.
Sprague Avenue & Wall Street – City Line Station 11
Work includes foundations for City Line amenities and ADA improvements.
- Utilities
- Subgrade preparation
- Concrete paving
Construction at this location is planned to be completed in June. View the traffic control plan here.
Main Avenue & Bernard Street – City Line Station 14
Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.
- Electrical work
- Water line work
- Demolition
Construction at this location is planned to be completed in June. View the traffic control plan here.
May 13 - May 20
Main Ave. & Bernard St. | Main Ave. & Howard St. | Sprague Ave. & Wall St. | First Ave. & Adams St. | Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St.
Pacific Avenue & Hemlock Street – City Line Station 3
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Platform curbing
Construction at this location is planned to be completed in June. View the traffic control plan here.
Pacific Avenue & Oak Street – City Line Station 5
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Street and platform curbing
- Bus pad construction
Construction at this location is planned to be completed in June. View the traffic control plan here.
First Avenue & Adams Street – City Line Station 6
Work includes utility improvements and paving on First Avenue to facilitate station installation.
- Brick gutter construction
Construction at this location is planned to be completed in mid May. View the traffic control plan here.
Sprague Avenue & Wall Street – City Line Station 11
Work includes foundations for City Line amenities and ADA improvements.
- Demolition work
- Utility work
Construction at this location is planned to be completed in June. View the traffic control plan here.
Main Avenue & Howard Street – City Line Station 12
Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.
- Tree well work
- Striping
Construction at this location is planned to be completed in June. View the traffic control plan here.
Main Avenue & Bernard Street – City Line Station 14
Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.
- Demolition work
- Waterline work
Construction at this location is planned to be completed in June. View the traffic control plan here.
May 6 - May 13
Mission Ave. & Cincinnati St. | Sprague Ave. & Wall St. | First Ave. & Adams St. | Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St. | Main Ave. & Howard St.
Cincinnati Street & Mission Avenue – City Line Road Work
Work includes road and traffic signal improvements at the intersection of Cincinnati Street and Mission Avenue to accommodate City Line buses.
- Demolition work
- Traffic signal work
- Paving
The intersection closure is planned to be completed by May 14. View the traffic control plan here.
Pacific Avenue & Hemlock Street – City Line Station 3
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Bus pad construction
- Platform curbing
Construction at this location is planned to be completed in June. View the traffic control plan here.
Pacific Avenue & Oak Street – City Line Station 5
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Bus pad construction
- Platform curbing
Construction at this location is planned to be completed in June. View the traffic control plan here.
First Avenue & Adams Street – City Line Station 6
Work includes utility improvements and paving on First Avenue to facilitate station installation.
- Demolition work
- Paving
Construction at this location is planned to be completed in mid May. View the traffic control plan here.
Sprague Avenue & Wall Street – City Line Station 11
Work includes foundations for City Line amenities and ADA improvements.
- Demolition work
Construction at this location is planned to be completed in June. View the traffic control plan here.
Main Avenue & Howard Street – City Line Station 12
Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.
- Gutter work
- Platform concrete
Construction at this location is planned to be completed in June. View the traffic control plan here.
April 30 - May 6
Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St. | Main Ave. & Howard St.
Pacific Avenue & Oak Street – City Line Station 5
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Demolition work
Construction at this location is planned to be completed in June. View the traffic control plan here.
Pacific Avenue & Hemlock Street – City Line Station 3
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Roadway grading
- Storm drain piping
- Waterline
Construction at this location is planned to be completed in June. View the traffic control plan here.
Main Avenue & Howard Street – City Line Station 12
Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.
- Platform footings
- Sidewalk
Construction at this location is planned to be completed in June. View the traffic control plan here.
April 23 - April 30
Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St. | Main Ave. & Howard St. | First Ave. & Monroe St. | Sprague Ave. & Monroe St.
Pacific Avenue & Oak Street – City Line Station 5
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Demolition work
Construction at this location is planned to be completed in June. View the traffic control plan here.
Pacific Avenue & Hemlock Street – City Line Station 3
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Roadway grading
- Storm drain piping
- Waterline
Construction at this location is planned to be completed in June. View the traffic control plan here.
Main Avenue & Howard Street – City Line Station 12
Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.
- Platform footings
- Sidewalk
Construction at this location is planned to be completed in June. View the traffic control plan here.
First Avenue & Monroe Street – City Line Station 8
Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.
- Signs and striping
Sprague Avenue & Monroe Street – City Line Station 9
Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.
- Signs and striping
April 16 - April 23
Pacific Ave. & Oak St. | Pacific Ave. & Hemlock St. | Main Ave. & Howard St. | First Ave. & Monroe St. | Sprague Ave. & Monroe St. | Maple St. & Pacific Ave.
Pacific Avenue & Oak Street – City Line Station 5
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Demolition work
- Tree trimming
Construction at this location is planned to be completed in June. View the traffic control plan here.
Pacific Avenue & Hemlock Street – City Line Station 3
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Demolition work
- Storm drainage
Construction at this location is planned to be completed in June. View the traffic control plan here.
Main Avenue & Howard Street – City Line Station 12
Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.
- Demolition work
- Bus pad construction
Construction at this location is planned to be completed in June. View the traffic control plan here.
First Avenue & Monroe Street – City Line Station 8
Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.
- Paving complete
- Platform and sidewalk concrete
Construction at this location is planned to be completed in late-April. View the traffic control plan here.
Sprague Avenue & Monroe Street – City Line Station 9
Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.
- Street paving complete
- Final sidewalk paving
Construction at this location is planned to be completed in late-April. View the traffic control plan here.
Maple Street & Pacific Avenue – Roadway Improvements
Work includes a public transit-rated roadway, pedestrian improvements, and new up-sized City waterline and stormwater improvements.
- Roadway open
- Paving complete
- Avista pole installation
April 9 - April 16
Pacific Ave. & Hemlock St. | Main Ave. & Howard St. | First Ave. & Monroe St. | Sprague Ave. & Monroe St. | Maple St. & Pacific Ave.
Pacific Avenue & Hemlock Street – City Line Station 3
Work includes foundations for City Line amenities, ADA improvements and landscape improvements.
- Intersection closure April 15 – June
- Traffic Control
Construction at this location is planned to be completed in June. View the traffic control plan here.
Main Avenue & Howard Street – City Line Station 12
Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.
- City waterline construction
- Demolition work
- Bus pad construction
Construction at this location is planned to be completed in June. View the traffic control plan here.
First Avenue & Monroe Street – City Line Station 8
Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.
- Bus pad
- Curbing
- Foundation construction
- Platform construction
- Paving
Construction at this location is planned to be completed in late-April. View the traffic control plan here.
Sprague Avenue & Monroe Street – City Line Station 9
Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.
- Foundation construction
- Platform construction
- Paving
Construction at this location is planned to be completed in late-April. View the traffic control plan here.
Maple Street & Pacific Avenue – Roadway Improvements
Work includes a public transit-rated roadway, pedestrian improvements, and new up-sized City waterline and stormwater improvements.
- Final grading of subgrade
- Paving
- Construct center island
Construction at this location is planned to be completed in mid-April. View the traffic control plan here.
April 2 - April 9
Main Ave. & Howard St. | First Ave. & Monroe St. | Sprague Ave. & Monroe St. | Maple St. & Pacific Ave.
Main Avenue & Howard Street – City Line Station 12
Work includes foundations for City Line amenities, ADA improvements and bike lane improvements.
- Demolition work
Construction at this location is planned to be completed in June. View the traffic control plan here.
First Avenue & Monroe Street – City Line Station 8
Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.
- Finalize waterline work
- Pour bus pad
- Curb preparation
Construction at this location is planned to be completed in late-April. View the traffic control plan here.
Sprague Avenue & Monroe Street – City Line Station 9
Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.
- Foundation curbing
- Platform curbing
Construction at this location is planned to be completed in late-April. View the traffic control plan here.
Maple Street & Pacific Avenue – Roadway Improvements
Work includes a public transit-rated roadway, pedestrian improvements, and new up-sized City waterline and stormwater improvements.
- Grading of subgrade
Construction at this location is planned to be completed in mid-April. View the traffic control plan here.


MArch 26 - April 2
First Ave. & Monroe St. | Sprague Ave. & Monroe St. | Maple St. & Pacific Ave.
First Avenue & Monroe Street – City Line Station 8
Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.
- Demolition work on First Avenue
- Waterline work
Construction at this location is planned to be completed in late-April. View the traffic control plan here.
Sprague Avenue & Monroe Street – City Line Station 9
Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.
- Bus platform construction
- Roadway grading
- Irrigation conduit behind platform
Construction at this location is planned to be completed in late-April. View the traffic control plan here.
Maple Street & Pacific Avenue – Roadway Improvements
Work includes a public transit-rated roadway, pedestrian improvements, and new up-sized City waterline and stormwater improvements.
- Curb and sidewalk work
- Grading of subgrade
Construction at this location is planned to be completed in mid-April. View the traffic control plan here.


MArch 19-26
First Ave. & Monroe St. | Sprague Ave. & Monroe St. | Maple St. & Pacific ave.
First Avenue & Monroe Street – City Line Station 8
Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.
- March 22 construction start
- Demolition work on First Avenue
- Waterline work
Construction at this location is planned to be completed in late-April. View the traffic control plan here.
Sprague Avenue & Monroe Street – City Line Station 9
Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.
- Light pole moved
- Utility work
- Roadway grading
Construction at this location is planned to be completed in late-April. View the traffic control plan here.
Maple Street & Pacific Avenue – Roadway Improvements
Work includes a public transit-rated roadway, pedestrian improvements, and new up-sized City waterline and stormwater improvements.
- Final storm and sewer work
- Curb and sidewalk work
Construction at this location is planned to be completed in mid-April. View the traffic control plan here.
MArch 12-19
Sprague Avenue & Monroe Street | Maple Street & Pacific avenue
Sprague Avenue & Monroe Street – City Line Station 9
Work includes foundations for City Line amenities, ADA improvements and minor landscaping improvements.
- Southern two lanes of Sprague Avenue closed between Monroe Street and Madison Street March 15 to April
- Utility and roadway work in preparation for a City Line station
Construction at this location is planned to be completed in late-April. View the traffic control plan here.
Maple Street & Pacific Avenue – Roadway Improvements
Work includes a public transit-rated roadway, pedestrian improvements, and new up-sized City waterline and stormwater improvements.
- Waterline install, pressure test and bacteria test
- Run new water services
- Storm water and sewer work
Construction at this location is planned to be completed in mid-April. View the traffic control plan here.
MArch 5-12
Pedestrian & Road Improvements ‐ Maple Street & Pacific Avenue
- Utility work including the setting of a new manhole and trenching for new waterlines
- Installation of waterlines, valves and services
- Waterline pressure test and chlorination
- Graded roadway to subgrade
Construction at this location is planned to be completed in mid-April. View the traffic control plan here.
Businesses remain open, please join STA in supporting local businesses throughout the construction season.


February 26 - March 5
Pedestrian & Road Improvements ‐ Maple Street & Pacific Avenue
- Construction of pedestrian and road improvements for City Line at the intersection of South Maple Street and West Pacific Avenue.
- Demolition of asphalt, curbing, and sidewalk, roadway grating, and preparation for water and sewer utility work.
Construction at this location is planned to be completed in mid-April. View the traffic control plan here.
Businesses remain open, please join STA in supporting local businesses throughout the construction season.


February 22-26
Pedestrian & Road Improvements ‐ Maple Street & Pacific Avenue
A full closure of the intersection of South Maple Street and West Pacific Avenue was put in place to accommodate utility work on Feb 22.
South Maple Street is closed from West 1st Avenue to Pacific Avenue and Pacific Avenue is closed from South Oak Street to South Maple Street. Pacific Avenue is also closed to thru traffic from South Cannon Street to South Oak Street.
Businesses remain open, please join STA in supporting local businesses throughout the construction season.
City Line road improvement construction begins at the same location on March 1 and is planned to be completed in mid-April.
This work will reconstruct the roadway. Benefits include a public transit-rated roadway, pedestrian improvements, and new up-sized City waterline and stormwater improvements.
Detour and construction signage are in place around the road closures and bus routes 60 and 61 are affected. Temporary bus stops are located at West 2nd Avenue and South Oak Street as well as West 2nd Avenue and South Chestnut Street, in place of stops along Pacific that are closed during construction. Visit SpokaneTransit.com for details.
The illustrations in the renderings are a conceptual representation of a City Line station. Some elements are subject to change pending the remaining design work.