Construction updates

November 25 - December 2

Phase I of construction is substantially complete.

Phase II amenity installation has begun. Active construction locations include: 

Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan

Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan

Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan

Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan

Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan

Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan

Station 14 Main and Bernard Eastbound. September 30 to November.

Station 15 at Riverside and Bernard Westbound. August 2 to September.  Traffic Control Plan

Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan

Station 18 at Main and Pines. August 29 to October. Traffic Control Plan 

Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.

Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.

Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan

Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.

Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.

Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan

Station 28 at Spokane Community College. September 1 to October.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

November 18 - November 25

Phase I of construction is substantially complete.

Phase II amenity installation has begun. Active construction locations include: 

Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan

Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan

Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan

Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan

Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan

Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan

Station 14 Main and Bernard Eastbound. September 30 to November.

Station 15 at Riverside and Bernard Westbound. August 2 to September.  Traffic Control Plan

Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan

Station 18 at Main and Pines. August 29 to October. Traffic Control Plan 

Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.

Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.

Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan

Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.

Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.

Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan

Station 28 at Spokane Community College. September 1 to October.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

November 11 - November 18

Phase I of construction is substantially complete.

Phase II amenity installation has begun. Active construction locations include: 

Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan

Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan

 

Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan

Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan

Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan

Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan

Station 14 Main and Bernard Eastbound. September 30 to November. 

Station 15 at Riverside and Bernard Westbound. August 2 to September.  Traffic Control Plan

Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan

Station 18 at Main and Pines. August 29 to October. Traffic Control Plan 

Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.

Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.

Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan

Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.

Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.

Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan

Station 28 at Spokane Community College. September 1 to October.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

November 4 - November 11

Phase I of construction is substantially complete.

Phase II amenity installation has begun. Active construction locations include: 

Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan

Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan

Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan

Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan

Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan

Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan

Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan

Station 14 Main and Bernard Eastbound. September 30 to November. 

Station 15 at Riverside and Bernard Westbound. August 2 to September.  Traffic Control Plan

Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan

Station 18 at Main and Pines. August 29 to October. Traffic Control Plan 

Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.

Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.

Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan

Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.

Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.

Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan

Station 28 at Spokane Community College. September 1 to October.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

October 28- November 4

Phase I of construction is substantially complete.

Phase II amenity installation has begun. Active construction locations include: 

Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan

Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan

Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan

Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan

Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan

Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan

Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan

Station 14 Main and Bernard Eastbound. September 30 to November. 

Station 15 at Riverside and Bernard Westbound. August 2 to September.  Traffic Control Plan

Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan

Station 18 at Main and Pines. August 29 to October. Traffic Control Plan 

Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.

Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.

Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan

Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.

Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.

Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan

Station 28 at Spokane Community College. September 1 to October.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

October 21- October 28

Phase I of construction is substantially complete.

Phase II amenity installation has begun. Active construction locations include: 

Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan

Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan

Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan

Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan

Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan

Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan

Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan

Station 14 Main and Bernard Eastbound. September 30 to November. 

Station 15 at Riverside and Bernard Westbound. August 2 to September.  Traffic Control Plan

Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan

Station 18 at Main and Pines. August 29 to October. Traffic Control Plan 

Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.

Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.

Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan

Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.

Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.

Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan

Station 28 at Spokane Community College. September 1 to October.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

October 14 - October 21

Phase I of construction is substantially complete.

Phase II amenity installation has begun. Active construction locations include: 

Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan

Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan

Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan

Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan

Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan

Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan

Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan

Station 14 Main and Bernard Eastbound. September 30 to November. 

Station 15 at Riverside and Bernard Westbound. August 2 to September.  Traffic Control Plan

Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan

Station 18 at Main and Pines. August 29 to October. Traffic Control Plan 

Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.

Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.

Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan

Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.

Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.

Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan

Station 28 at Spokane Community College. September 1 to October.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

October 7 - October 14

Phase I of construction is substantially complete.

Phase II amenity installation has begun. Active construction locations include: 

Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan

Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan

Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan

Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan

Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan

Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan

Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan

Station 14 Main and Bernard Eastbound. September 30 to November. 

Station 15 at Riverside and Bernard Westbound. August 2 to September.  Traffic Control Plan

Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan

Station 18 at Main and Pines. August 29 to October. Traffic Control Plan 

Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.

Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.

Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan

Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.

Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.

Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan

Station 28 at Spokane Community College. September 1 to October.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 

September 30 - October 7

Phase I of construction is substantially complete.

Phase II amenity installation has begun. Active construction locations include: 

Station 6 at First and Adams Eastbound. August 1 to September. Traffic Control Plan

Station 8 at First and Monroe Eastbound. August 1 to September. Traffic Control Plan

Station 9 at Sprague and Monroe Westbound. August 1 to September. Traffic Control Plan

Station 10 at Sprague and Wall Westbound. August 3 to September. Traffic Control Plan

Station 11 at Wall and Sprague Northbound. August 3 to September. Traffic Control Plan

Station 12 at Main and Howard Eastbound. August 10 to October. Traffic Control Plan

Station 13 Riverside and Stevens Westbound. August 9 to September. Traffic Control Plan

Station 14 Main and Bernard Eastbound. September 30 to November. 

Station 15 at Riverside and Bernard Westbound. August 2 to September.  Traffic Control Plan

Station 17 at Riverside and Division Westbound. August 2 to September. Traffic Control Plan

Station 18 at Main and Pines. August 29 to October. Traffic Control Plan 

Station 19a Spokane Falls Blvd at WSU Eastbound. September 22. Periodic road closure.

Station 19b Spokane Falls Blvd at WSU Westbound. September 26. Periodic road closure.

Station 20 at Cincinnati and Springfield. August 31 to October. Traffic Control Plan

Station 21a Cincinnati and Desmet Southbound. September 19. Periodic road closure.

Station 21b Cincinnati and Desmet Northbound. September 20. Periodic road closure.

Station 22 at Mission and Columbus. September 5 to October. Traffic Control Plan

Station 28 at Spokane Community College. September 1 to October.

Businesses remain open, please join STA in supporting local businesses throughout the construction season. 